K11 flexible waterproof coating is a two-component polymer waterproof coating, which is a mixture of powder and additives. After scraping, it forms a layer of flexible waterproof film, which has good adhesion with concrete and mortar base, and can form a tight, firm, and long-lasting bond with it.
Product number: LD-2203
Product specifications: 17KG 8.5KG
Construction technology
1. Grassroots cleaning
Ensure that there are no sand particles or looseness at the grassroots level
2. Wet base layer
No clear water at the grassroots level is sufficient
3. Mixed products
First, pour the liquid material into the bucket and slowly add the powder while stirring. Stir evenly to complete the process
4. Applying slurry
Apply 2 to 3 times, with a time interval between each coat. The previous coat should be dry and not sticky. The direction of the previous coat should be aligned, and each coat should be perpendicular
Common problems during construction
Phenomenon: Pores appear after coating application
1. The base layer is dry and not sufficiently wetted;
2. High temperature construction, surface drying too fast;
3. Uneven mixing and excessive thickness of one-time coating.
Phenomenon: Sanding occurs after waterproofing construction
1. The base layer is too dry and the wall humidity is low;
2. The coating is not dry, and the maintenance period needs to be extended;
3. Failure to mix and match products correctly.
Phenomenon: After waterproofing construction, there is a phenomenon of grout return and insufficient quality
1. High environmental humidity, high substrate humidity, and slow drying speed;
2. One application is too thick.
Phenomenon: Surface condensation occurs after waterproofing construction
1. In a high humidity environment, the moisture content of the base layer is high;
2. There is a large temperature difference between day and night.
Matters needing attention
1. The temperature during construction should be between 5 ° C and 35 ° C, and outdoor construction is prohibited on windy or rainy days; In case of low temperature and high humidity weather, it is necessary to extend the re coating maintenance time appropriately to achieve the best coating effect.
2. The slurry after opening should be used up within 2 hours.
3. Wet the base surface with clean water before construction, but there should be no exposed water on the base surface.
4. The storage temperature of liquid components should not be lower than 0 ° C.
5. Do not mix the dried adhesive with water before use.
6. Before construction, please carefully read the construction instructions.
7. Please use appropriate protective measures during construction, such as gloves.